May 22,2023
Pars Oil and Gas Company was assigned by the National Iranian Oil Company to complete the second phase of a plan to develop the South Pars Gas Field’s oil layer in the Persian Gulf, the managing...
-
May 16,2023
Pars Oil and Gas Company, as an employer, is close to finalizing an agreement with Nargan Company, as a contractor, to conduct feasibility studies on boosting pressure in the South Pars Gas Field...
-
April 30,2023
South Pars Gas Complex in Bushehr Province supplies 10,000 tons of ethane on a daily basis to petrochemical plants located in the region, the managing director of the complex said.
Calling it the...
-
April 02,2023
Gas production from the giant South Pars Gas Field’s Phase 11 will start this year, the managing director of the National Iranian Oil Company said.
“Last autumn, we decided to drill four wells in...
-
February 08,2023
The production capacity of South Pars fourth refinery will increase in the near future, the director of the refinery said.
Noting that the rise in output has been planned to prevent gas shortage...
-
January 31,2023
South Pars Gas Complex in Bushehr Province has produced 700,000 barrels of gas condensates per day during the first 10 months of the current Iranian year (March 21, 2022-Jan. 20), director of...
-
December 06,2022
The development of the giant South Pars Gas Field’s Phase 11 is underway and the phase will soon become operational, managing director of the National Iranian Oil Company said.
“The drilling of...
-
November 20,2022
The project to build a gas condensate concentration unit at the third refinery of South Pars Gas Field for feeding the mercaptan unit is underway, which will raise the annual output of gas odorants...
-
November 19,2022
Natural gas supply shortfall in Iran is expected to surpass 400 million cubic meters per day by 2030, a professor at the Sharif University of Technology said.
“Daily gas shortfall is currently 240...
-
November 12,2022
Pars Oil and Gas Company is planning to drill 35 wells in South Pars to increase gas production in the huge field that Iran shares with Qatar, the deputy head of POGC’s Reservoir Operations...
-
November 09,2022
The construction of the South Pars Gas Field’s last onshore refinery in Asalouyeh, Bushehr Province, is complete.
Mohsen Khojastehmehr, managing director of the National Iranian Oil Company, made...
-
November 02,2022
The second refinery of South Pars Gas Complex (belonging to phases 2 and 3) increased its sweet gas and sulfur output in the first half of the current Iranian year (March-September) compared with...
-
August 26,2022
The first phase of an operation to lay a new offshore pipeline to link the first deck of Phase 16 (SPD 16A) of South Pars Gas Field in the Persian Gulf to onshore gas refining facilities has been...
-
August 14,2022
Subsea pipe-laying operations to connect the offshore platform B of South Pars Phase 11 [SPD 11B] to onshore gas processing facilities are complete.
Based on information from Pars Oil and Gas...
-
July 20,2022
The drilling of wells at Phase 11 of South Pars Gas Field in the Persian Gulf is near completion and it is expected to start production in winter, managing director of the National Iranian Oil...
-
July 11,2022
Operations to develop South Pars Gas Complex in Bushehr Province are underway with the aim of enhancing gaseous products’ exports and storage, managing director of the gas complex said.
“SPGC is...
-
June 22,2022
The only incomplete phase of the South Pars Gas Field in the Persian Gulf, Phase 11, will start production in September, the oil minister said.
Iranian experts and engineers are developing the...
-
June 21,2022
A total of 19 widely used equipment in South Pars Gas Field platforms will be indigenized by the end of October.
-
June 08,2022
The ninth refinery of the South Pars Gas Complex is almost self-sufficient in the manufacture of equipment and parts used in the refinery, the deputy director of the complex said.
-
May 20,2022
The first shipment of butane, a form of liquefied petroleum gas, produced in Phase 13 of South Pars Gas Field has been exported from Siraf Pars Port on the Persian Gulf coast, manager of South Pars...
-
May 06,2022
An estimated 14 million cubic meters of natural gas per day will be extracted from Phase 11 of the South Pars Gas Field in the Persian Gulf by the end of the current Iranian year (March 2022-23),...
-
April 05,2022
The conversion of Besat single-cycle power station in Asalouyeh in Bushehr Province to a combined-cycle facility was completed on Tuesday, the managing director of Pars Oil and Gas Company, a...
-
March 16,2022
The National Iranian Oil Company has assigned Iran Marine Industrial Company (SADRA) the task of completing the third development phase of the South Pars Gas Field's oil layer, managing director of...
-
January 28,2022
The cumulative output of natural gas and its byproducts from the South Pars Gas Field in the Persian Gulf has reached 2 trillion cubic meters since 2002, the operations manager of Pars Oil and Gas...
-
January 10,2022
Development operations to lay subsea pipelines and install the platforms of Phase 11 of the South Pars Gas Field in the Persian Gulf have gained momentum, the contractor of SP Phase 11 said.