-
September 09,2020
South Pars Gas Complex produces 650,000 barrels of gas condensates per day, a major part (500,000 barrels) of which is piped to the Persian Gulf Star Refinery in Hormozgan Province to be converted...
-
August 30,2020
Gas extraction from the giant South Pars Gas Field in the Persian Gulf increased 150% over the last decade, managing director of Pars Oil and Gas Company said.
“Output capacity has approached 700...
-
August 23,2020
Gas production from the third platform of South Pars Gas Field Phase 13 started on Friday, the operator said.
“Gas from the satellite platform 13C is transferred to the 13A main platform via an 18...
-
June 01,2020
The sixth natural gas processing plant in South Pars Gas Complex will increase production this year (started in March), director of the refinery said.
“Projects include installing new air...
-
May 22,2020
Installation work on the first wellhead jacket of South Pars Gas Field Phase 11 in the Persian Gulf started Thursday.
The jacket of Platform B of Phase 11, which was hauled from Qeshm Island on...
-
May 17,2020
Pressure reduction has gradually started in South Pars Gas Field Phase 12 and could extend other phases within five years, managing director of Pars Oil and Gas Company said Sunday.
“Despite peak...
-
May 11,2020
Gas flaring in phases 17 and 18 of the giant South Pars Gas Field in the Persian Gulf has reduced by 50% to help preserve the environment, head of South Pars’s seventh refinery said.
“With the...
-
May 02,2020
The onshore refinery of South Pars Gas Field Phase 14 in the Persian Gulf will come on stream by June 2021, the program manager of the phase said.
“The project to construct the refinery has...
-
April 21,2020
Programs are underway to increase output from South Pars Gas Field phases 20 and 21. Work is expected to be completed in the second half of this year, managing director of the 8th South Pars...
-
April 15,2020
Hook up operations on offshore decks of phase 13 (SPD 13A and 13C) of South Pars Gas Field in the Persian Gulf have been delayed due to problems created by the coronavirus, managing director of...
-
March 15,2020
The drilling rig of Phase 11 of South Pars Gas Field will be put on its jacket in a few months and drilling will begin in June.
Phase 11 is scheduled to be developed in two integrated and...
-
March 08,2020
To fast track production in the South Pars Gas Field off the Persian Gulf, the last offshore platform of its Phase 13 (13C) was installed on Saturday.
According to Payam Motamed, operator of Phase...
-
February 24,2020
The platform jacket for the Phase 11 of South Pars Gas Field is ready in Qeshm Island and will be installed on its location in the Persian Gulf before the current Iranian year is out (March 19),...
-
February 17,2020
Gas condensate output from the South Pars Gas Field in the first 10 months (March-Dec 2019) of the currency fiscal year increased by 5% compared to the corresponding period a year ago, managing...
-
February 11,2020
Decks 13A and 13C of South Pars Gas Field Phase 13 were loaded at the Iran Marine Industrial Company, also known as SADRA, in Bushehr Province on Monday.
-
February 01,2020
The last offshore deck of Phase 14 (14D) was installed on Saturday to boost output from the South Pars Gas Field, the development manager said.
“As soon as hookup operations are over, the new...
-
January 07,2020
To speed up gas production from South Pars Gas Field in the Persian Gulf, an offshore deck of phase 23 was linked to Iran Gas Trunkline (IGAT) on Tuesday, deputy operator of the phases said.
“The...
-
December 27,2019
To boost output from the South Pars Gas Field, the third offshore deck of Phase 14 started natural gas production on Friday, the development manager said.
“The new platform (14B) has added 14...
-
December 04,2019
Exports from South Pars Gas Field off the Persian Gulf in the eighth month of the fiscal year (Oct. 23-Nov. 23) increased by 39% in volume compared to the same period last year, head of the customs...
-
November 25,2019
Natural gas production in the giant South Pars Gas Field in the Persian Gulf will increase by 70 million cubic meters per day before the calendar year is out, managing director of Pars Oil and Gas...
-
November 20,2019
Domestic gas consumption jumped to new highs on Tuesday reaching 693 million cubic meters per day, dispatching director at the National Iranian Gas Company said.
Mehdi Jamshidi Dana said...
-
November 13,2019
To fast track gas production from South Pars Gas Field in the Persian Gulf, offshore platforms of phases 23 and 24 were installed on Wednesday.
Deck 23 and the satellite rig 24B, each weighing 2,...
-
October 20,2019
Gas production at one of the platforms of the giant South Pars Gas Field off the Persian Gulf, which had been damaged, has been fully repaired, the operations manager of Pars Oil and Gas Company...
-
October 11,2019
The last offshore platform of South Pars Gas Field phases 22-24 was successfully loaded at Iran Marine Industrial Company, also known as SADRA, in Bushehr Province Thursday.
With a capacity to...
-
September 15,2019
Domestic companies will start operations to develop Phase 11 of the South Pars Gas Field in the Persian Gulf in October, managing director of Pars Oil and Gas Company, a subsidiary of state-owned...