The second gas sweetening train of the South Pars Gas Field's Phase 13 in Persian Gulf will go on stream in April, less than a month of implementing its first train, the director of Phase 13 development project said.
"The phase's development has registered a work-in-progress rate of 89%, with the onshore project being 92% complete," Payam Motamed was also quoted as saying by Shana.
The official added that offshore platforms are 85% complete, offshore pipe-laying has registered a 78% progress and drilling has advanced by 86%.
The refining unit will receive sour gas from phases 6, 7 and 8 as part of Iran’s production plan from the world’s largest gas field that is shared with Qatar.