To further boost output from South Pars Gas Field in the Persian Gulf, the third offshore deck of the field’s Phase 14 was installed on Saturday, the development manager of the phase said.
“After completion of operations, namely hookup, commissioning, and maritime pipelines, the deck will start extraction in November,” the Oil Ministry news portal Shana quoted Mohammad Mehdi Tavassolipur as saying.
Deck 14B was loaded on June 11 and transferred to its designated offshore spot. Weighing 1,450 tons, the structure is located 105 km off the Persian Gulf.
When operational, the deck will extract 14 million cubic meters of natural gas per day from the field. 