April 19,2023
The last stage of the production test in Jofeir and Sepehr oilfields in Khuzestan Province was successfully completed on Tuesday, the managing director of Pasargad Energy Development Company said...
-
December 21,2022
The development of Azar Oilfield in Ilam Province is underway and the project will be handed over to the West Oil and Gas Production Company in the near future, the managing director of the Iranian...
-
November 11,2022
The development of the first phase of South Azadegan Oilfield in Khuzestan Province has been undertaken by the Petroleum Engineering and Development Company and is expected to be completed by...
-
October 13,2022
The development plan of Mansouri Oilfield in Khuzestan Province is underway and three wells (122, 123 and 124) have started production in the first half of the current Iranian year (March-September...
-
August 30,2022
The development project of Nargesi Oilfield in southern Iran has been assigned to Dana Energy Company to produce 6,000 barrels of oil per day in about 40 months.
After the project’s completion,...
-
August 27,2022
Production from Sohrab Oilfield near the Iran-Iraq border in the southern Khuzestan Province will start in the near future, managing director of the National Iranian Oil Company said.
“The Sohrab...
-
August 13,2022
The expansion of Changouleh Oilfield near the Iraqi border in Ilam Province has started and drilling operations will end in October, the head of Exploration Department at the National Iranian Oil...
-
July 25,2022
Pars Oil and Gas Company is carrying out exploration in the Persian Gulf for new oil and gas fields.
“Out of four exploratory operations planned till today, two have finished their initial stages...
-
July 05,2022
The development of joint Azadegan Oilfield in Khuzestan Province will be completed with an investment of $7 billion, Oil Minister Javad Owji said.
"The integrated development plan of Azadegan...
-
June 20,2022
Two more wells in Danan Oilfield in Ilam Province have been drilled and with the successful completion of tests, they are now ready to start production, the manager of maintenance projects in...
-
May 31,2022
The development of two wells at the Mansouri Oilfield in Khuzestan Province is complete, said the managing director of Oil Industries' Engineering and Construction Group, contractor of the...
-
May 15,2022
The National Iranian Oil Company has planned to increase the output of Azadegan Oilfield in Khuzestan Province to 570,000 barrels of oil per day, NIOC’s director of integrated planning said.
“...
-
May 14,2022
The first phase of Jofeir and Sepehr oilfields’ development plans in Khuzestan Province will be completed in November, managing director of Pasargad Energy Development Company said.
“The fields’...
-
April 23,2022
The first well as a part of the development program of Forouzan offshore oilfield in the Persian Gulf has become operational, director of the field development project at the Iranian Offshore Oil...
-
April 20,2022
Drilling operations to boost Jofeir and Sepehr oilfields’ production capacity in Khuzestan Province are being carried out by the private sector, deputy managing director of Pasargad Energy...
-
February 11,2022
Efforts are underway to increase the production capacity of South Azadegan Oilfield in Khuzestan Province by 15,000 barrels per day by the end of the current Iranian year (March 20), managing...
-
February 02,2022
The total production of Azar Oilfield, which Iran shares with Iraq, has reached 50 million barrels in five years, said the managing director of Sarvak Azar Engineering and Development Company, the...
-
December 28,2021
The development of South Azadegan Oilfield in Khuzestan Province is expected to be completed in 2023, managing director of the National Iranian Oil Company said.
“Upon the project’s completion,...
-
December 28,2021
A project to collect 405 million cubic meters of associated petroleum gas per year from Maroun 3, Maroun 6 and Mansouri oilfields was unveiled on Sunday.
The project will be carried out with a...
-
September 24,2021
The Oil Ministry has invested around $10 billion on the development of Azar joint oilfield in Ilam Province to increase the output from the field, which currently stands at 65,000 barrels per day,...
-
July 31,2021
The project to link Khesht Oilfield in Fars Province to Bandar Genaveh Terminal in Bushehr Province via a 100-kilometer pipeline will be completed by the end of the current Iranian year (March 20,...
-
July 11,2021
The first phase of the project to collect associated petroleum gas from the Maroun 3 Oilfield in Khuzestan Province is operational now and its second phase as well as the project to collect APG...
-
June 23,2021
The first well drilled in the Asmari reservoir of Abuzar Oilfield in the Persian Gulf to increase crude oil production has now become operational, the head of petroleum engineering at the Iranian...
-
May 30,2021
The first phase of Khesht Oilfield development in Fars Province will go on stream in the summer, managing director of South Zagros Oil and Gas Production Company said on Sunday.
"Phase 1...
-
May 16,2021
Oil extraction from the shared West Karoun block in southern Khuzestan Province has reached 420 barrels per day – a six-fold increase compared to 2013.