The Goureh-Jask crude oil pipe-laying operation has been completed and welding is in the final stages, managing director of the Petroleum Engineering and Development Co., a subsidiary of the National Iranian Oil Company, said.
“Close to 1,000 km of pipes are in place and first phase of the project is scheduled to come on stream by May. It will transfer 300,000 barrels of crude oil a day from Goureh oil terminal in Bushehr Province to Jask Port in Hormozgan Province,” Mehr News Agency quoted Touraj Dehghani as saying.
The pipes were made by three Iranian companies, he said, and added that Ahvaz Industrial Pipe Company, the Isfahan-based Mobarakeh Steel Company and Khuzestan Oxin Steel Company were involved.