The operation of the first gas sweetening train of Phase 14 refinery in the giant South Pars Gas Field by January 2022 is of high priority for the National Iranian Oil Company, the company’s deputy for production said.
“Due to rising gas consumption in the country and in order to prevent gas shortage in winter, the launch of Phase 14 refinery is very important,” Farrokh Alikhani added.
Units, including steam boilers and gas condensate storage facilities, have become operational in the phase, while other sections, namely instrument air unit and gas sweeteners, are near completion. The construction of the overall facility has made over 90% progress.